Services/Reaching design capacity

The plant is commissioned but doesn’t reach design capacity?

I bring spray dryers to design performance — on your real product.

Finished production hall
01

Sound familiar?

  • The plant was handed over, but real production isn’t running
  • Output is lower than calculated in the design
  • Frequent stops for washing and repairs
  • The manufacturer’s service worked its hours and left
02

Why it happens

The manufacturer’s service works to a fixed plan and a limited number of hours. The real product often differs from the sample the manufacturer used to develop the process — different composition, different viscosity, different behaviour in the tower. When product problems start, the manufacturer’s obligations under the contract are already fulfilled.

03

What I do

  1. 01

    The whole line

    I examine feed preparation, evaporation and drying

  2. 02

    Real concentrate

    I compare it with what the plant was designed for

  3. 03

    Bottlenecks

    In equipment, operating parameters and staff practices

  4. 04

    Adjustment

    Operating parameters and, if needed, modification of units

  5. 05

    Handover

    Instructions and operator training

04

What you get

A plant at design capacity. Instructions and protocols your team uses to hold the result after I leave.

05

Project

Equipment delivery Chamber pre-assembly Foundation Drying chamber installation Equipment installation Building frame Cladding Finished production hall

Equipment delivery

Case 02Meat processing, animal protein powders · Eastern Europe · 2022 · General contractor

A 4,500 m³ plant delivered turnkey — on second-hand equipment and a quarter of the original budget

Challenge

Build and commission a complete drying plant: spray dryer, powder storage silo, CIP station and cleaning system, and filling and packaging machine.

    Root cause

    The company dropped its bank investment loan and financed construction from working capital. With the budget cut fourfold, all equipment was bought second-hand — condition unknown and without engineering documentation for the new site.

      What was done

      Ran the project from procurement to start-up: work planning, installation supervision and commissioning.

      • As project manager, organised procurement of components, approved the plant layout and set up on-site fabrication of steel structures and assemblies
      • As supervisor, oversaw the mechanical and electrical installation of the process equipment and the building
      • As consultant, ran pre-commissioning diagnostics and resolved technical and process issues
      • Adjusted evaporation, atomisation and cleaning parameters and trained the operators

      Result

      The plant reached 100% of design capacity.

      • Full scope delivered: building construction, process line installation and commissioning
      • Product quality is consistent and in strong demand
      • The plant was built and commissioned without any bank financing
      Project manager · Supervisor · Consultant18 months

      Confirmed by a written reference from the plant owner

      Free express analysis

      A free express analysis of your dryer

      • The likely cause of the problem
      • What to check first
      • Whether a site visit is needed — or remote recommendations are enough

      Send photos and video — I’ll reply in writing within 3 working days.

      No calls, no obligations. NDA on request. Write in English or Russian.